Three steps to a successful data center migration plan


Shally Bansal Stanley, Contributor
09.30.2008
Rating: -3.00- (out of 5)


Systems Channel Update
Digg This!    StumbleUpon Toolbar StumbleUpon    Bookmark with Delicious Del.icio.us    Add to Google


Solution provider takeaway: Solution providers need to know the three steps to a successful data center migration plan and how to mitigate clients' business risks.

Data center migration plans top the list of key projects for most CIOs this year, next year and even the year after that. Data center migration is center-stage on a three-year plan and highly visible within an organization. Why the spotlight?

As you know, data centers cost a lot of money, and data center migrations present a tremendous amount of risk to a business. Your data center manager customers are transitioning from operations to risk management roles overnight, with little training and no tolerance for failure.

Data center migration is an exercise in risk mitigation. Investing the appropriate time and money in planning, execution and testing to protect the business is definitely money well spent. The question becomes, how do you best protect your customer's business?

The steps outlined below, which have proven successful in large and small data center migration plans, focus on keeping applications up and running throughout the project.

Step 1: Know what you're migrating before you build your plan.

Data centers are complicated. The combination of densely populated racks housing a variety of hardware, running all kinds of software, and cabling running amok sounds like a nightmare, but it accurately describes more than 95% of corporate data centers.

The biggest mistake people make when planning a data center migration is to establish move timelines and budgets before collecting data about what is actually in the data center. I don't mean determining whether it's a production or QA environment -- I mean, what's actually in the data center.

It's all about the applications. Business runs on the applications that sit in a data center. Before you touch them (let alone unplug something) you need to fully understand the following for each application:

  • Application owners
  • Planned upgrades or changes
  • Allowable downtime
  • Server, network, storage and operating system requirements
  • Power specs
  • Connectivity (cabling) diagrams
  • Rack layout

After understanding the business needs, you can develop a data center migration strategy that outlines the type of move (swing vs. forklift), the duration for the move, and finally the anticipated cost for the move.

More data center resources
Next-generation data centers aim for virtualized everything

Microsoft System Center handles data center management

Getting pushback from customers to do it faster and cheaper without increasing downtime? Walk them through the data center applications and ask them how long they think the migration should take and what the consequences of downtime really are. Can they afford the risk of faster and cheaper?

Step 2: Prove that your detailed plan supports service-level agreements (SLAs).

A successful data center migration plan is based upon a solid migration plan that factors in overall program management, IT infrastructure, facilities planning and coordination, application migration and lots of contingency planning.

Successful migrations always have a highly orchestrated plan executed by people who have data center migration experience. That's the easy part.

The hard part is proving that the application won't "break" during the migration. Breaking an application means experiencing degraded performance or downtime outside of acceptable SLA limits. Creating a contingency plan for the application migration is essential to winning the confidence of the business so that the migration can take place. The more comfortable application owners are with the plan (and recovery), the more cooperative they will be. Their participation is critical from both a technical and functional perspective. You will need their help in the following areas:

Technical

  • Understanding the application architecture and dependencies
  • Validating the applications maps and inventories
  • Testing the application once it's been moved

Functional

  • Understanding planned application releases and upgrades
  • Listing restrictions for peak seasonal activity, if any
  • Identifying customer SLAs that must be met
  • Quantifying the business impact of downtime

Proving that your plan mitigates application downtime risk to the business is critical to the success of your data center migration plan.

Step 3: Test and report on success and failure.

Testing and reporting are critical components of a data center migration plan but are often understaffed and poorly funded -- at least until something breaks. Solid testing and reporting offer the best insurance against production breakage. You just have to do it.

The best planning in the world does not remedy poor execution. Excellent execution does not remove the need for testing. And testing twice is better than testing once.

Organizations that regularly migrate applications rely on solid staging, testing and reporting mechanisms to ensure they minimize application disruption (downtime). They know the ultimate success measures of a data center migration are staying within budget, staying on time and minimizing disruption. It's important to report testing results with application owners and highlight any problems you find so that you can jointly resolve them prior to the actual migration.

Following these three guidelines doesn't guarantee that the data center migration will be easy, but it will bring the seemingly impossible plan into the realm of the successful.

About the author
Shally Bansal Stanley is a managing director at Acumen Solutions Inc., a business and technology consulting firm with offices across the United States and in Europe. Shally is a recognized leader in data center solutions within the industry. She can be reached at sstanley@acumensolutions.com.


Rate this Tip
To rate tips, you must be a member of SearchSystemsChannel.com.
Register now to start rating these tips. Log in if you are already a member.




Digg This!    StumbleUpon Toolbar StumbleUpon    Bookmark with Delicious Del.icio.us    Add to Google


RELATED CONTENT
Data Centers and Server Rooms
Beware of hidden costs in server consolidation or virtualization
Data center migration quiz: Forklift vs. swing
Data center migration quiz results: Forklift vs. swing
Best strategies for cooling server rooms at SMBs
Best techniques for cooling blade servers
Strategies for cooling a server room: Flooring, cabling, budget
Microsoft System Center handles data center management
Best practices for server room design services
Systems products to pay attention to
How many data centers are you planning to virtualize, and where?

Computer Hardware
Factors to consider when using blade servers for virtualization
Beware of hidden costs in server consolidation or virtualization
Choosing a Unix-based blade server
Countering the top five blade server objections
Profiting from iPhone application development
Evolving power supplies, batteries address energy management concerns
Evolving power supplies, batteries address energy management concerns
Microsoft System Center handles data center management
iPhone Exchange ActiveSync makes iPhone viable for businesses
Best practices for server room design services

RELATED RESOURCES
2020software.com, trial software downloads for accounting software, ERP software, CRM software and business software systems
Search Bitpipe.com for the latest white papers and business webcasts
Whatis.com, the online computer dictionary

DISCLAIMER: Our Tips Exchange is a forum for you to share technical advice and expertise with your peers and to learn from other enterprise IT professionals. TechTarget provides the infrastructure to facilitate this sharing of information. However, we cannot guarantee the accuracy or validity of the material submitted. You agree that your use of the Ask The Expert services and your reliance on any questions, answers, information or other materials received through this Web site is at your own risk.

HomeTopicsITKnowledge ExchangeTipsMultimediaWhite PapersBlogsEvents
About Us  |  Contact Us  |  For Advertisers  |  For Business Partners  |  Site Index  |  RSS
SEARCH 
TechTarget provides enterprise IT professionals with the information they need to perform their jobs - from developing strategy, to making cost-effective IT purchase decisions and managing their organizations' IT projects - with its network of technology-specific Web sites, events and magazines.

TechTarget Corporate Web Site  |  Media Kits  |  Reprints  |  Site Map




All Rights Reserved, Copyright 2006 - 2008, TechTarget | Read our Privacy Policy
  TechTarget - The IT Media ROI Experts